UC San Diego Hillcrest || Project Status

 

March 28th, 2023 – UC San Diego Hillcrest Outpatient Pavilion and Parking Garage project is progressing well, despite the challenges presented with this unprecedented rainy season. The team is continuing with the parking structure, producing about a quarter of a parking deck every 10 days, 1 level at a time. The Outpatient Pavilion structure foundations are set and interior walls are being built, and structural steel installation begins April 2023, marking a huge milestone for the project. This is just the beginning at Hillcrest, Intelisyn has provided logistics, cost analysis, and construction management services as UC San Diego propels into their Hillcrest Campus development.