Milestone Alert | NTPLLN Crane Demo

5058 NTPLLN B2 Crane Removal 011120015058 NTPLLN Progress Photo 020520015058 NTPLLN Progress Photo 02052003

February 12, 2020 – !!MILESTONE ALERT!! Cranes are coming down at UC San Diego’s North Torrey Pines Living & Learning Neighborhood (NTPLLN). Tower crane at Building 2 was demobilized January 10th through 12th and Building 1 tower crane is scheduled to be demobilized February 21st. Building 5 will top out on February 14th, which will be the final building on site to top out. A topping-off ceremony is scheduled for Monday, February 10th. Congrats to all project teams and personnel for an awesome milestone achievement!