City of Hope || DOC Status

March 22, 2023 – Rain, rain, rain. Even with relentless weather to start 2023, the City of Hope Duarte Outpatient Center (DOC) project is pressing on into Spring. The DOC project topped out last October, and it’s been full speed ahead on interior framing and rough MEPs (AHUs being set on the roof!). As you can see, the exterior skin is coming along on this 400k SF Cancer Clinic. Intelisyn has been on this one since the beginning, providing programming, planning, logistics, cost analysis, and construction management services.  We look forward to a strong finish and being able to welcome City of Hope patients and staff into this new facility.